Leia o texto abaixo para responder às questões de 1 a 4

Real Life Accident: Anchor Damages Hull, Bow Thruster Compartment Flooded

November 27, 2015 byMarsreport

Recently , a f reight ship was underway in 15 foot seas

when the forepeak flood alarms activated. The crew

investigated and discovered the starboard anchor had slipped

10-15 links, causing it to strike and puncture the hull.

5 As a result, seawater flooded the bow thruster and

emergency fire pump compartment. The casualty resulted in

excess of $1 million in vessel damage and a month's lost

revenues while the vessel was out of Service undergoing

repair.

10 During the repair period, it was discovered that the

anchor windlass brake pad had worn down to 2-3mm thickness.

With only this amount of pad, the fully applied brake could

not achieve its designed holding power. The crew should have

recognised the excessive wear to the brake pads and that these

15 required replacement. It was also discovered that the anchor

involved in the incident was a replacement, and had different

specifications to the original anchor.

The replacement anchor's relative position in the hawse

pipe was not the same as the original, be cause the shank

20 length and connecting linkages were different. The size

difference prevented the riding pawl from properly engaging

the anchor chain. As an added safety device, a wire sling had

been used to secure the anchor while at sea. The wire sling

was threaded through a chain link and secured to the vessel

25 with a pelican hook.

When the sling broke and the brake failed, the anchor' s

weight and the ship's movement then caused it to drop before

the riding pawl could properly engage. The sling failure was

likely caused by the corrosion of the inner wire strands; the

30 inner wire strands being exposed to the elements because of

the sharp bend in the wire. Although the wire sling was

inspected regularly, those performing the inspections were not

instructed on how to examine and determine its serviceability,

35 Lessonslearned

  1. All preventative maintenance prograrames should be up to date

and include specific language on anchor windlass equipment,

particularly emphasising when brake assemblies must be renewed

or adjusted,

40 . When key vessei components, such as anchors, are to be

replaced, a proper review should be undertaken and all

possible variables consídered.

  1. Persons involved with vessei maintenance and repair should

have the technical resources available to them in order to

45 assist in determining serviceability or replacement of

shipboard equipment.

{Adaptedfrom:www.marineinsight.com)



Choose the optíon that correctly completes the blanks of the text below, respectively.

A fire occurred in the generator room _______ the vessel was at se a, depriving the vessel of all ______ emergency auxiliary power supplies. The crew fought the fire by using the vessel’s fixed Halon installation and dry powder apparatus. _________ less than an hour the fire was extinguished. No injuries were experienced. ____ ;_____ , due to the fire, the vessel lost her maín propulsion power and had to be towed to port. (Casualty Information/ 1997)


A

whilst / but / During/ However


B

once / and / After / When


C

and / soon / Thus / Since


D

for / to / Furthermore / Although


E

despite / so / Consequentl.y / With